One University Place Construction Update 5
02/14/16
The upper deck for the second floor has been poured and we will begin seeing more construction on the condominiums on the second floor. Concrete block walls for the first floor have been completed. Plumbing and electrical work continues on the lower lever and the first floor. These areas are heated and enables construction to progress at a good pace.
Cold weather has slowed some of the outside work. A landscaping plan for the east ravine should be completed in March. The City Council and residents will be looking at
drawings for the
addition of a left hand turning lane on Melrose into the development and the
modification of the Sunset-Melrose intersection for greater efficiency at a
Public Hearing on March 8.
Attached to this
report is the portion of the February 2016 City Engineer’s report to City
Council that relate to the OUP project, and to the public improvements project
for the Sunset/Melrose intersection. MMS Engineering has submitted Public Improvements
Plan drawings. There is also a link to a water main improvement document that
was the subject of council discussion. At this time a route for the water main
has not been decided. Also attached is City Building Inspector Terry Goerdt’s
update in the February 2016 Building/Zoning/Sanitation Report. The McComas-Lacina
minutes of the weekly construction update meeting for 2-10-16 is also included.