One University Place Construction Update 6
03/11/16
Framing on the second and third floor is progressing.
Construction on the roof will begin shortly which will enclose the front
building. Foundations for the ramp into the lower parking level have been
poured. Plumbing and electrical installation continues on all levels.
Installation of the Brick Veneer on the front part of the building will begin
shortly. Installation of metal doorway frames throughout the building has
begun.
The landscaping plan for the east ravine was submit by the developer and consultants to
the City Council and approved. Once the proper slope for the ravine is achieved
and confirmed then installation of trees, bushes and ground cover will begin.
The plans for the left hand turning lane on Melrose, Sunset/Melrose
intersection improvements, median installation on Sunset and the underground
water piping on Sunset were approved by the City Council and have been let out
for bid. Details on these items can be found in the March 4th
construction update. Council expects to review bids and let the contract on
March 29 at a special meeting. The outline for this process is contained in the
March
2016 Engineer’s Report to
City Council. Also included here is
·
McComas Lacina progress meeting minutes of
2/24/16.
·
Community Center Space DRAFT layout